Macon Campus Traffic Re-routed Due to Construction

789

Due to construction at the new Science and Engineering Bldg site,
traffic on College and Prince Streets will have to be rerouted. In order
to minimize the inconvenience, construction on these streets will be
completed in two phases:
 
Phase 1 – Feb 4th thru Feb 24th – Prince Street will be blocked between
the Mercer Health Systems parking lot and College Street. To view a map
of the affected area and the alternate route, please click on the
following link:
 
        /About_Mercer/MaconMap/phase1.htm
 
Phase 2 – Feb 24th thru April 15th – The south end of College Street
will be blocked between Prince Street and the entrance to the parking
lot above the School of Engineering. To view a map of the affected area
and the alternate route, please click on the following link:
 
        /About_Mercer/MaconMap/phase2.htm
 
        Detour signs will be put in place at the end of this week to to guide
everyone from the South Campus entrance of College Street (at Mercer
University Drive) to the North Campus entrance of College Street (at
Coleman Avenue). Questions should be directed to Mercer Police at
478-301-2970.